Midland Ave. & 8th Street Construction -
Sanitary Sewer Force Main Project Information
* UPDATED 8/23/10
The City of Glenwood
Springs contracted with Martinez Western Constructors, Inc. to construct the approximately 2
miles of dual 16" force main that is needed to extend the sewer system from
the current treatment plant to the new regional wastewater treatment facility
being constructed in west Glenwood.
As of June 30, 2010, the majority of the line has been constructed. Two
major pieces remain: Midland Avenue from Red Mountain to 8th street, and crossing the 8th Street Bridge to the site of a future lift station.
8th Street Bridge is OPEN!
Paving Operations are scheduled for
August 27th and 28th
(Some delays can be expected during this time)
This website will be updated to reflect the current activities and schedule for
the project.
For more information, please call the city engineering department at 384-6435
Thanks for your patience and understanding during this construction project.